French maritime engineering specialist Iroise Mer, based in Brest on the country’s northwestern coast, used a 50t Straightpoint Radiolink plus (RLP) load cell during a refit of a tanker mooring system located 500m off the Corsica coast, recently.
Iroise Mer accepted a scope of work to update the site, comprising four different mooring lines, complete with anchors, chains and concrete deadweights. All existing components had to be removed and new ones installed. The RLP was used to measure pre-tension up to 30t to check new anchors were properly installed into the seabed.
The RLP was positioned between the anchor line (or chain) and the towing cable on a vessel, attached with two Green Pin shackles. Straightpoint does have a product for measuring tension on lines, the Running Line Dynamometer...
Read More